Balcón al Mar, Jávea, 2024-2025

A full renovation, inside and out: the living area moves from the upper floor to the ground floor, with a large opening and a new kitchen. The garden and entrance have been completely redesigned.

See the result as a slideshow
The pool and the large wooden pergola

Before and after

The house, from the pool side

The original house and its pool with an ochre edge
Before
The whitewashed house, its large openings and the renovated pool
After

The pergola

The old pergola on its columns
Before
The new wooden pergola and its outdoor kitchen
After

The pool

The pool and the original tiling
Before
The renovated pool, its light flooring and the pergola
After

The garden

The original garden, bare earth under the palm trees
Before
The redone garden, with its lawn under the palm trees
After

The entrance

The original entrance, under a stone arch
Before
The redone entrance, its white arch and pine door
After

The ground floor

The original ground floor, its bar, white tiling and arched windows
Before
The renovated ground floor, white and bright, with its sofa and table
After

The kitchen

The old kitchen, narrow and dark
Before
The new kitchen, its wooden units and island
After

A bedroom

An original bedroom
Before
A renovated bedroom, its carved headboard and wooden wardrobes
After

The round room upstairs, now two bathrooms

The round room upstairs during the work, its black beams and red floor
Before
One of the two bathrooms, with blue-green tiles under the beams
After

The work, month by month

From the first demolition, in May 2024, to the lawn laid in February 2025.

  1. The pool is rebuilt.

    May 2024
    The pool is rebuilt.

  2. The interior is demolished.

    May 2024
    The interior is demolished.

  3. Props support the structure to create the large opening.

    June 2024
    Props support the structure to create the large opening.

  4. The niches are built on site.

    July 2024
    The niches are built on site.

  5. Upstairs, the round room is stripped back.

    September 2024
    Upstairs, the round room is stripped back.

  6. The rounded fireplace takes shape under the beams.

    November 2024
    The rounded fireplace takes shape under the beams.

  7. An old carved door becomes a headboard.

    December 2024
    An old carved door becomes a headboard.

  8. The entrance and garden are completely rebuilt.

    December 2024
    The entrance and garden are completely rebuilt.

  9. The lawn is laid.

    February 2025
    The lawn is laid.

The result

The outdoor kitchen under the pergola
The outdoor kitchen under the pergola
The living room, open to the outdoors
The living room, open to the outdoors
A bedroom under the beams
A bedroom under the beams
A rounded fireplace and its niches
A rounded fireplace and its niches
An upstairs terrace
An upstairs terrace
The second bathroom and its stone basins
The second bathroom and its stone basins